PdfPrep.com

What should the agile practitioner do?

During a project’s last few sprints, an agile practitioner notices an increase in defects. A root-cause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.

What should the agile practitioner do?
A . Inform the product owner’s manager so that corrective action may be taken.
B . Communicate this to the product owner, and offer to help facilitate discussions with the team.
C . Encourage a team member to raise this during the retrospective to ensure that the product owner is aware.
D . Escalate this issue to the sponsor so that corrective action may be taken.

Answer: B

Exit mobile version