A senior team member feels underutilized.
What should the agile practitioner do?
A . Transfer the senior member to another team that will more fully utilize their skill set.
B . Conduct a performance evaluation to determine whether or not this member is a team player.
C . Encourage the project team to involve the senior member in more project activities.
D . Ask the functional manager to determine the best course of action.
Answer: C
Explanation:
Reference: https://www.pmi.org/learning/library/team-morale-motivation-ideas-maintain-6175