An agile team has only one database administrator with the necessary knowledge of database-related tasks. The project manager identifies the risk that if this person leaves, team velocity will significantly decrease.
What should the agile coach do?
A . Start the hiring process for a new, equally skilled database administrator as a replacement.
B . Move this database administrator to another team so that team members learn database-related tasks.
C . Add another database administrator to balance the workload and aid with knowledge retention.
D . Obtain agreement from the team that, on upcoming sprints, the database administrator will act only in an advisory capacity.
Answer: A