What should project assurance do next?

During stage 3, the team manager reports that the work to update the ‘corporate quality procedures’ has been completed and the product is ready to be delivered.

What should project assurance do next?
A . Update the team plan to show that the work package is complete.
B . Check the work package and follow the procedure to deliver completed products.
C . Verify that all the products to be delivered by the work package are approved.
D . Update the stage plan to show the work package as completed.

Answer: C