What should be verified next?

Scenario: The new CISO was informed of all the Information Security projects that the section has in progress. Two projects are over a year behind schedule and way over budget. Using the best business practices for project management, you determine that the project correctly aligns with the organization goals.

What should be verified next?
A . Scope
B . Constraints
C . Resources
D . Budget

Answer: A