The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10, 20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks.
What sequence type would you use to create the second sequence in the system?
A . Substitute sequence
B . Alternative sequence
C . Parallel sequence
D . Standard sequence
Answer: B