You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program.
What program management process is management asking you to perform?
A . Contract administration
B . Resource management
C . Resource control
D . Procurement management
Answer: C