What Product Owner activities occur between the end of the current Sprint and the beginning of the next Sprint?

What Product Owner activities occur between the end of the current Sprint and the beginning of the next Sprint?
A . Product Backlog refinement.
B . Updating stakeholders on project progress.
C . There are no such activities. When the current Sprint ends, the new Sprint begins.
D . Participate as a team member at the Sprint Retrospective.

Answer: C