What Product Owner activities occur between the end of the current Sprint and the beginning of the next Sprint?
A . Product Backlog refinement.
B . Updating stakeholders on project progress.
C . There are no such activities. When the current Sprint ends, the new Sprint begins.
D . Participate as a team member at the Sprint Retrospective.
Answer: C