Posted by: Pdfprep
Post Date: December 9, 2020
During the execution phase of a project a defect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect.
What process was applied?
A . Change request
B . Risk response
C . Risk management plan
D . Lessons learned
Answer: B
Leave a Reply