A company needs to change a report design file to reflect new business requirements. The report administrator updates the BIRT file accordingly.
What process must be utilized to deploy it in Maximo?
A . Application Importing
B . Report Administration Importing
C . Rebuild Maximo EAR and deploy
D . Apply Configuration Changes in Database Administration
Answer: B
Explanation:
References: https://www.ibm.com/developerworks/community/wikis/home?lang=en#!/wiki/IBM%20Maximo%20Asset% 20Management/page/Administering%20BIRT%20Reporting