What process is used by the Project Manager to maintain focus on delivery of a stage’s products within agreed tolerances?
A . Directing a Project
B . Controlling a Stage
C . Managing a Stage Boundary
D . Managing Product Delivery
Answer: B
What process is used by the Project Manager to maintain focus on delivery of a stage’s products within agreed tolerances?
A . Directing a Project
B . Controlling a Stage
C . Managing a Stage Boundary
D . Managing Product Delivery
Answer: B