What must you do for each of these materials?


You procure some materials exclusively by consignment. You want material requirements planning (MRP) to create consignment purchase requisitions assigned to a vendor, instead of normal purchase requisitions for these materials.

What must you do for each of these materials? There are 2 correct answers to this question.
A . Set a special MRP group for consignment in the material master record.
B . Maintain a default storage location for external procurement in the material master record.
C . Set a special procurement key/type for consignment in the material master record.
D . Create at least one source of supply for consignment.

Answer: C,D