A . Create a potentially shippable product Increment that includes at least one piece of functionality.
B . Analyze and estimate the requirements for the subsequent Sprints.
C . Create a project plan in order to map functional development to Sprint dates.
D . Only design and develop the architecture and infrastructure.

Answer: A

Explanation:

Sprints promote iterative and incremental development.