A program manager concurrently implements a software program at four client locations . The client’s objective is to maintain quality while shortening the software implementation timeline.
What key elements should be included in the benefits register to achieve this goal?
A . Plans for tracking and communicating risks associated with the program
B . Plans for conducting program quality assurance and control on a regular basis
C . Plans for program schedule control to meet the shorter timeline
D . Plans for defining metrics and key performance indicators (KPIs), and procedures to measure benefits.
Answer: D