Refer to Case 3.
You are sizing the compute capacity of blade servers in a converged infrastructure solution with the following specifications:
• Number of cores: 12
• Processor speed: 3.1 GHz
• Utilization percentage: 70%
What is the total GHz processing capability of two blade servers?
A . 28.4
B . 31.6
C . 52.0
D . 75.6
Answer: C
Explanation:
processing capability= cores x processor speed x percentage use
pc = 12 x 3.1 x 0.70 = 26.04 x 2 blades = 52.08