PdfPrep.com

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
A .  0.50
B .  0.67
C .  1.50
D .  2.00

Answer: A

Exit mobile version