B, a construction company, has a policy of carrying out a post completion audit on every construction project undertaken where the value exceeds $1 million.
What is the role of the post completion audit?
A . To reward staff and celebrate success.
B . To signify the end of the project.
C . To highlight what can be done to improve similar future projects.
D . To apportion blame for things not done well.
Answer: C