A company is releasing a new product geared toward a specific geographic area . The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained.
What is the program manager’s next step?
A . Assign project managers and resources
B . Classify the program’s benefits
C . Identify the program sponsor and program stakeholders
D . Develop the program business case
Answer: C