PdfPrep.com

What is the primary objective of the daily scrum?

What is the primary objective of the daily scrum?
A .  To share with the team what each member has completed in the Sprint, what each member will work onnext, and to report progress roadblocks
B .  To give a status report to the Product Owner on what each member has completed in the Sprint, what eachmember will work on next, and to report progress roadblocks.
C .  To discuss work details with the team since every team member must attend the meeting
D .  To give a status report to the Scrum Master on what each member has completed in the Sprint, what eachmember will work on next, and to report progress roadblocks.

Answer: A

Exit mobile version