PdfPrep.com

What is the most likely type of change management would make to this program scope?

Gary is program manager for his organization. His current program is over budget and is slipping on the program schedule. Management has demanded a change to the program scope.

What is the most likely type of change management would make to this program scope?
A . A change to add additional funds to the program scope
B . A change to reduce the program scope
C . Anything that management demands
D . A change to add additional time to the program schedule

Answer: B

Exit mobile version