You have configured Resource Governor with three resource pools. You have assigned the first resource pool a minimum CPU and memory value of 20%. You have assigned the second resource pool a minimum CPU and memory value of 30%. You want to assign maximum CPU and memory values to the third resource pool.
What is the maximum CPU and memory value you can assign to this resource pool?
A . 30%
B . 50%
C . 70%
D . 100%
Answer: B
Explanation:
The maximum resource value assigned to the third pool is 100%; the sum of the minimum resource values assigned to the other pools is 50%.