What is the goal of the ‘assess – estimate’ step?

What is the goal of the ‘assess – estimate’ step?
A . Identify the threats and opportunities facing the organizational activity
B . Estimate and agree the budget required to manage risks to the activity
C . Assess the effectiveness of the risk management processes within an organization
D . Determine the risks with the greatest effect on activities objectives

Answer: D