What is the first thing an agile development team should do when planning an iteration?
A . Assign the tasks to one team member.
B . Separate the stories into tasks.
C . Estimate the stories’ tasks.
D . Help establish the next sprint’s goal.
Answer: B
Explanation:
Reference: https://resources.collab.net/agile-101/agile-sprint-planning-iteration-planning