What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
A . $50
B . $100
C . $125
D . $175
Answer: C
Explanation:
Estimate to completion calculates how much more of the budget is needed to complete the project if everything continues at the current level of performance.
EAC ‘atypical’ = AC + BAC – EV
EAC ‘typical’ = AC + ((BAC – EV) / CPI)