Posted by: Pdfprep
Post Date: November 29, 2020
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
A . $50
B . $100
C . $125
D . $175
Answer: C