What is the difference between verified and accepted deliverables?
A . Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.
B . Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.
C . Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.
D . Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process
Answer: A
Explanation:
Reference: https://www.brainbok.com/guide/pmp/study-notes/verification-vs-validation/