What is the critical path of the project?

Posted by: Pdfprep Category: CAPM Tags: , ,

Using the following information and assuming that the project team will work a standard 40-hour work week:

Activity A has a duration of 10 days.

Activity B has a duration of 10 days and its predecessor is Activity A.

Activity C has a duration of 15 days and its predecessor is Activity A.

Activity D has a duration of 10 days and its predecessor is Activity B and C.

Activity E has a duration of 10 days and its predecessor is Activity D.

Activity F has a duration of 15 days and its predecessor is Activity D.

What is the critical path of the project?

A. ABDE

B. ACDF

C. ABDF

D. ACDE

Answer: B