Using the following information and assuming that the project team will work a standard 40-hour work week:
Activity A has a duration of 10 days.
Activity B has a duration of 10 days and its predecessor is Activity A.
Activity C has a duration of 15 days and its predecessor is Activity A.
Activity D has a duration of 10 days and its predecessor is Activity B and C.
Activity E has a duration of 10 days and its predecessor is Activity D.
Activity F has a duration of 15 days and its predecessor is Activity D.
What is the critical path of the project?
A. ABDE
B. ACDF
C. ABDF
D. ACDE
Answer: B