You want to use the different options for planning in SAP ECC.
What is the correct sequence of the planning procedures?
A . Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planning
B . Demand management -> Sales and operations planning -> Capacity planning -> Long-term planning -> Material requirements planning
C . Material requirements planning -> Demand management -> Sales and operations planning -> Long-term planning -> Capacity planning
D . Long-term planning -> Sales and operations planning -> Demand management -> Material requirements planning -> Capacity planning
Answer: A