Posted by: Pdfprep
Post Date: November 1, 2020
You have been assigned to perform a hardware installation of three G560 nodes in a 4-post rack.
However, only static rails are included with this shipment.
What is the best way to proceed?
A . Order sliding rails, since these are required for the installation
B . Install cable management arms in the rack
C . You cannot proceed because these nodes cannot be installed in 4-post rack
D . Proceed directly because these nodes can be installed in a 4-post rack
Answer: D