PdfPrep.com

What is an input to this process?

A project manager is formalizing acceptance of the completed project deliverables.

What is an input to this process?
A . Verified deliverables
B . Validated deliverables
C . Accepted deliverables
D . Completed change requests

Answer: A

Explanation:

Reference: https://www.oreilly.com/library/view/a-guide-to/9781935589679/sub5.5.xhtml

Exit mobile version