A project manager is formalizing acceptance of the completed project deliverables.
What is an input to this process?
A . Verified deliverables
B . Validated deliverables
C . Accepted deliverables
D . Completed change requests
Answer: A
Explanation:
Reference: https://www.oreilly.com/library/view/a-guide-to/9781935589679/sub5.5.xhtml