What is a reliable technique for estimating the scope and cost of a software-development project?

Posted by: Pdfprep Category: CISA Tags: , ,

What is a reliable technique for estimating the scope and cost of a software-development project?
A . Function point analysis (FPA)
B . Feature point analysis (FPA)
C . GANTT
D . PERT

Answer: A

Explanation:

A function point analysis (FPA) is a reliable technique for estimating the scope and cost of a software-development project.