What is a purpose of the Initiating a Project process?
A . Delegate day-to-day management of the project to the Project Manager
B . Answer the question: do we have a viable and worthwhile project?
C . Understand the work that needs to be done to deliver the project’s products before committing to a significant spend
D . Enable the Project Board to be provided with sufficient information so that it can review the success of the current stage
Answer: C