Posted by: Pdfprep
Post Date: February 9, 2021
A client wants to perform some analysis, start development, and finish with testing.
What is a common risk of this development practice?
A . User Acceptance Testing and Development happen in parallel but Functional Testing occurs at the end of the project.
B . One major release occurs at the end of the project so it is hard to track which features were integrated.
C . Testing occurs at the end. which typically leaves no time left to perform bug fixes.
D . Development and OA happen at the same time, but one major release occurs at the end without any user input.
Answer: A