What happens if the Development Team cannot complete its work by the end of the Sprint?
A . The Sprint is extended and future Sprints use this new duration.
B . The Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this length.
C . The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.
Answer: B