Below is a business process model for a goods ordering process:
What error has been made in this diagram?
A . The arrowed flow mine from Fulfil order should go to the end node ( the bull eye) not to the task received:
B . The arrowed flow line from Complete order should go to check stock availability not to the decision diamond.
C . The task’Complete order’s should be In only one swimlane, as tasks straddling two swim lanes are not permitted.
D . The task’ Cancel order’ should be rename Order cancelled as by this point in the process the order has been cancelled.
Answer: B