The Scrum Master must ensure that a sustainable pace is maintained throughout every Sprint.
What does sustainable pace mean in the context of Scrum?
A . Effort spent in each Sprint increases gradually, as the team gains momentum to deliver.
B . Effort spent in each Sprint decreases gradually, as the team becomes more familiar with the expected deliverables.
C . Effort expended in the present Sprint is similar to the effort spent on the previous Sprints, and is a comfortable pace for the team.
D . Effort spent in the Sprint is directly proportional to the cost incurred in the Sprint.
Answer: B