What does SAP Activate recommend to keep team members informed and aligned? Please choose the correct answer.
A . Daily status meeting with project manager
B . Daily team stand-up meeting
C . Daily e-mail status updates to project manager
D . Daily progress review meeting with sponsor
Answer: B