What does it mean for the production planner when MRP works with infinite capacities?
A . MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
B . MRP creates capacity requirements without checking the capacity of a work center.
C . MRP creates capacity requirements only if the work center has sufficient capacity.
D . MRP assigns capacity requirements automatically after the last scheduled order on a work center.
Answer: B