What document provides a record of the risks identified for a particular activity?
A . Risk progress report
B . Risk register
C . Risk management strategy
D . Risk improvement plan
Answer: B
What document provides a record of the risks identified for a particular activity?
A . Risk progress report
B . Risk register
C . Risk management strategy
D . Risk improvement plan