You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its projects.
What document is management asking you to create in this instance?
A . Requirements document
B . Project charter
C . Business case
D . Scope statement
Answer: D