What do you use to schedule operations from planned orders so that the production plan can be fulfilled?
A . Demand Planning (DP)
B . Material Requirements Planning (MRP)
C . Capacity Requirements Planning (CRP)
D . Supply Network Planning (SNP)
Answer: B