What do you use the check Conflict button for? NOTE: There are 3 correct answers to this question
A . Adjustment of distribution of staffing
B . Adjustment of dates of roles
C . Adjustment of work according to roles assignment of a task
D . Adjustment of work according to resource availability
E . Adjustment of dates of staffing
Answer: A,B,E