What do you have to consider, when you use the ATP (Available To Promise) checks for material? (Choose two)

What do you have to consider, when you use the ATP (Available To Promise) checks for material? (Choose two)
A . ATP checks can be carried out automatically when releasing a production order.
B . ATP checks are automatically performed during Material Requirements Planning (MRP) runs.
C . ATP checks are used to evaluate the free capacity on a certain work center.
D . ATP checks are mandatory for lead-time scheduling.
E . ATP checks can be adjusted to also consider future requirements and receipts.

Answer: A,E