What do you have to consider regarding consumption? (Choose two)
A . Consumption takes place on the material level between the planned independent requirements and the planned orders.
B . Consumption is restructured with the planning run.
C . Consumption can take place between order reservations and planned independent requirements, depending on the strategy.
D . Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
Answer: C,D