The above performance report shows the earned value (EV) analysis for a program .

The program director performs a high-level analysis and must present a summary narrative to the steering committee.

What do the current findings show?
A . Project C is running behind schedule and is over budget; projects A, B, and D are on schedule.
B . Project A is running ahead of schedule and is under budget; projects B, C, and D are behind schedule.
C . The overall program is performing within an acceptable level of variance.
D . Project A is running behind schedule and is over budget; projects B, C, and D are on schedule.

Answer: D