Company A is working on implementing a new platform with multiple stakeholders. The business analyst has gathered the requirements and established a baseline. However, scope creep is a persistent
problem.
What could the business analyst have established to help manage this situation?
A . Configuration management system
B . Sponsor signoff
C . Change control process
D . Communication plan
Answer: C