The agile team disagrees with the business stakeholders on completing some epics.
What could help eliminate misunderstandings?
A . Agree on requirements with all stakeholders
B . Begin planning every four iterations
C . Consider previous sprint demo feedback when planning the next sprint
D . Include the reasons for the project in the contract
Answer: C