You have assigned two resources to the same role resource 1 to calendar week 10 and

resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.

What could be a reason for the system behavior?
A . The role demand for the timeframe is too low
B . The flexible Assignment indicator is active for the rile type in customizing
C . The edit in parallel indicator is inactive for the role type in customizing
D . The assigned effort for either of the resourceassignedis to high

Answer: C